POLLUTION CONTROL BOARD : ASSAM BAMUNIMAIDAM : GUWAHATI-21 |
||||||||||||||||||||||||||||||||||||||||||||
Name
of the Project |
EIA Reports
& Executive Summary |
Date
& Venue of Public Hearing |
||||||||||||||||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
|
|
||||||||||||||||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||
|
Proposed Expansion Projects of Cement Manufacturing Unit from production capacity of 600TPD to 1200TPD by M/s Cement Corporation of India Ltd. at village-Bokajani, Karbi Anglong District Assam. Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Karbi Anglong district; District Industry Centre, Karbi Anglong district; Bokajan Town Committee, Karbi Anglong District Assam; Chief Executive Officer, Zilla Parishad, Diphu, Karbi Anglong District, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Golaghat & PCBA Head Office, Guwahati. |
Public Hearing to be held at Bidya Sagar High School, P.O.-Bokajan, District -Karbi Anglong, Assam 08-09-2011 at 11:00AM |
||||||||||||||||||||||||||||||||||||||||||
|
Proposed Projects of M/s DART Energy (AS) Pte. Ltd., Village-Likhapani, Tehsil-Margherita, Tinsukia District Assam. Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Tinsukia district; District Industry Centre, Tinsukia district; Lekhapani Gaon Panchayat, , Dibrugarh District Assam; Chief Executive Officer, Zilla Parishad, Tinsukia, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati. Minutes of Public Hearing is available in DC office, Tinsukia district; District Industry Centre, Tinsukia district; Lekhapani Gaon Panchayat, , Dibrugarh District Assam; Chief Executive Officer, Zilla Parishad, Tinsukia, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati.
|
|
||||||||||||||||||||||||||||||||||||||||||
|
Proposed Projects of M/s Oil India Ltd., Duliajan, Dibrugarh District Assam. Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Dibrugarh/Tinsukia district; District Industry Centre, Dibrugarh district; Rongagora/Chiringghola/Hapjan Gaon Panchayat, , Dibrugarh/Tinsukia District Assam; Chief Executive Officer, Zilla Parishad, Dibrugarh/Tinsukia, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati. Minutes of Public Hearing dated 23-08-2011 ,25-08-2011, 26-08-2011 is available in DC office, Dibrugarh/Tinsukia district; District Industry Centre, Dibrugarh district; Rongagora/Chiringghola/Hapjan Gaon Panchayat, , Dibrugarh/Tinsukia District Assam; Chief Executive Officer, Zilla Parishad, Dibrugarh/Tinsukia, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati.
|
|
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Naphtha Units (160,000TPA) of Petrochemical Grade Naphtha by M/s. Numaligarh Refinery Ltd. Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Golaghat district; District Industry Centre, Golaghat district; Pangka Gaon Panchayat, PO-Kanaighat, Golaghat District Assam; Chief Executive Officer, Zilla Parishad, Golaghat, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Golaghat & PCBA Head Office, Guwahati. Cover Page,Index- I, Index II , Chapter-I, Chapter-II Chapter-III(1-58),Chapter-III(59-80),Chapter-III(81-117), Chapter-IV, Chapter-V, Chapter-VI, Annexure b) Proposed Wax Units to produce 43,300TPA of Paraffin Wax and 4,500TPA of Semi-Microcrystalline Wax Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Golaghat district; District Industry Centre, Golaghat district; Pangka Gaon Panchayat, PO-Kanaighat, Golaghat District Assam; Chief Executive Officer, Zilla Parishad, Golaghat, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Golaghat & PCBA Head Office, Guwahati. Cover Page,Index-I, Index - II , Chapter-I, Chapter-II Chapter-III, Chapter-IV, Chapter-V, Chapter-VI, Drawing- Annexure , Plate 2.1 Minutes of Public Hearing is available in DC office, Golaghat district; District Industry Centre, Golaghat district; Pangka Gaon Panchayat, PO-Kanaighat, Golaghat District Assam; Chief Executive Officer, Zilla Parishad, Golaghat, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Golaghat & PCBA Head Office, Guwahati. |
14-07-2011 at 11:00AM (Public Hearing held at Pangka Roopram Hazarika High School, P.O. - Kanaighat, Telgram, District - Golaghat, Assam ) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Secondary Tank Farm Project in Tengakhat-Nahakatia-Jorajan area. Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Dibrugarh district; District Industry Centre, Dibrugarh district; Naoholia Gaon Panchayat, , Dibrugarh District Assam; Chief Executive Officer, Zilla Parishad, Dibrugarh, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati. Cover
Page,Acknowledgement,Content, Chapter-1, Chapter-Fig 1.1 Chapter-Fig 1.2,Chapter- fig 1.3, Chapter-2, Chapter-3, Chapter-Fig 3.1, Chapter-Fig 3.2,Chapter-Fig 3.3, Chapter-Fig 3.4, Chapter-4 ,Chapter-4 Table 4.1,Chapter-4 Table 4.2,Chapter-4 Table 4.3,Chapter-4 Table 4.5,Chapter-4 Table 4.6,Chapter-4 Table 4.7,Chapter-4 Table 4.8,Chapter-4 Table 4.9,Chapter-4 Table-4.10,Chapter-4 Table 4.11,Chapter-4 Table 4.12,Chapter-4 Table 4.13,Chapter-4 Table 4.14,Chapter-4 Table 4.15-16,Chapter 4 Table 4.17,Chapter 4 Table 4.18,Chapter 4 Table 4.19,Chapter 4 Table 4.20,Chapter 4 Table 4.21-22,Chapter 4 Table 4.23,Chapter 4 U Fig 4.1,Chapter 4 U Fig 4.2,Chapter-5,Chapter-6,Chapter-7,Chapter-7 fig 7.1,Chapter-8, Chapter-8 table 8.1
Minutes of Public Hearing is available in DC office, Dibrugarh district; District Industry Centre, Dibrugarh district; Naoholia Gaon Panchayat, , Dibrugarh District Assam; Chief Executive Officer, Zilla Parishad, Dibrugarh, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati.
b) Proposed 3(three) Pipeline Projects in Tinsukia and Dhola area : 37km long 400mm dia Gas Transmission Pipeline from Baghijan to CGGS and OTP near W/50; 45 km long 200mm dia Baghjan STF Crude Oil Pipeline; 23 km long 100mm dia Crude Oil Pipeline from Baghjan to Makum OCS.
Executive
Summary (in English)
Executive
Summary (in Assamese)
EIA
Report is available in DC office,Tinsukia district; District Industry Centre, Tinsukia district;Baghajan Gaon Panchayat, Tinsukia District Assam; Chief Executive Officer, Zilla Parishad, Tinsukia, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati.
Cover
Page,Acknowledgement,Content, Chapter-1, Chapter-1.1 Chapter-1.2,Chapter-1.3,Chapter-1.4, Chapter-2, Chapter-3, Chapter-4 ,Chapter-4.1,Chapter-4.2,Chapter-4.3,Chapter-4.4,Chapter-4.5,Chapter-4.6,Chapter-4.7,Chapter-4.8,Chapter-4.9,Chapter-4.10,Chapter-4.11,Chapter-4.12,Chapter-4.13,Chapter-4.14,Chapter-4.15,Chapter-4.16,Chapter-4.17,Chapter-4.18,Chapter-4.19,Chapter-4.20,Chapter-4.21,Chapter-4.22,Chapter-5,Chapter-5.1,Chapter-5.2,Chapter-6,Chapter-7,Chapter-7.1,Chapter-8
Minutes of Public Hearing is available in DC office, Tinsukia district; District Industry Centre, Tinsukia district;Baghajan Gaon Panchayat, Tinsukia District Assam; Chief Executive Officer, Zilla Parishad, Tinsukia, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati. |
|
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Pulp Plant (250TPD), Paper Plant (250TPD) & 10MW Cogeneration Power Plant atIndustrial Growth Center, Matia, District - Goalpara, Assam by M/s Kohinoor Pulp & Paper Pvt. Ltd.(K.P.P.P.L). Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Goalpara district, District Industry Centre, Goalpara district, Mornai Gaon Panchayat, Chief Executive Officer, Zilla Parishad, Goalpara, Assam, MoEF Regional Office at Shillong,PCBA Regional Lab-cum-Office, Bongaigaon & PCBA Head Office, Guwahati. Cover Page,Content, Chapter-I, Chapter-II Chapter-III, Chapter-IV, Chapter-V, Chapter-VI, Chapter-VII,Chapter-VIII, Chapter-IX, Chapter-X Minutes of Public Hearing is available in DC office, Goalpara district, District Industry Centre, Goalpara district, Mornai Gaon Panchayat, Chief Executive Officer, Zilla Parishad, Goalpara, Assam, MoEF Regional Office at Shillong,PCBA Regional Lab-cum-Office, Bongaigaon & PCBA Head Office, Guwahati. |
20-05-2011 at 11:00AM (Public Hearing held at Sardar Ballav Bhai Patel High School, Marnoi, Goalpara, Assam ) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Cement Plant (600 TPD) at dag No. 85 & 86, K. P. Patta Assam by M/s GMG Cement Industries. Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Kamrup(M) district, District Industry Centre, Kamrup district, 57 No. Barkhat Gaon Panchayat, Chief Executive Officer, Zilla Parishad, Kamrup, Assam, MoEF Regional Office at Shillong,PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. Cover Page,Frontpage, Preface, Index, Chapter-I, Chapter-II Chapter-III, Chapter-IV, Chapter-V, Chapter-VI, Chapter-VII,Chapter-VIII Minutes of Public Hearing is available in DC office, Kamrup(M) district, District Industry Centre, Kamrup district, 57 No. Barkhat Gaon Panchayat, Chief Executive Officer, Zilla Parishad, Kamrup, Assam, MoEF Regional Office at Shillong,PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. |
03-03-2011 at 11:00AM (Public Hearing held at Open space in front of M/s Balaji Silicate Industies, Vill- Sarutari, Byrnihat, District - Kamrup, Assam ) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Naphtha Units (160,000TPA) of Petrochemical Grade Naphtha by M/s. Numaligarh Refinery Ltd. Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Golaghat district; District Industry Centre, Golaghat district; Pangka Gaon Panchayat, PO-Kanaighat, Golaghat District Assam; Chief Executive Officer, Zilla Parishad, Golaghat, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Golaghat & PCBA Head Office, Guwahati. Cover Page,Index- I, Index II , Chapter-I, Chapter-II Chapter-III(1-58),Chapter-III(59-80),Chapter-III(81-117), Chapter-IV, Chapter-V, Chapter-VI, Annexure b) Proposed Wax Units to produce 43,300TPA of Paraffin Wax and 4,500TPA of Semi-Microcrystalline Wax Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Golaghat district; District Industry Centre, Golaghat district; Pangka Gaon Panchayat, PO-Kanaighat, Golaghat District Assam; Chief Executive Officer, Zilla Parishad, Golaghat, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Golaghat & PCBA Head Office, Guwahati. Cover Page,Index-I, Index - II , Chapter-I, Chapter-II Chapter-III, Chapter-IV, Chapter-V, Chapter-VI, Drawing- Annexure , Plate 2.1 |
14-02-2011 at 2:00PM (Public Hearing held at Pangka Rupam Hazarika High School, P.O. - Kanaighat, Telgram, District - Golaghat, Assam ) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Cement Manufacturing Units (360 TPD) at dag No. 87, K. P. Patta Assam by M/s Rudradev Cement Pvt. Ltd. Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Nagaon district; District Industry Centre, Nagaon district; Bheloguri Gaon Panchayat, Nagaon, Assam; Chief Executive Officer, Zilla Parishad,Nagaon, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. Cover Page,Frontpage, Preface, Index, Chapter-I, Chapter-II Chapter-III, Chapter-IV, Chapter-V, Chapter-VI, Chapter-VII,Chapter-VIII, Annexure Minutes of Public Hearing is available in DC office, Nagaon district; District Industry Centre, Nagaon district; Bheloguri Gaon Panchayat, Nagaon, Assam; Chief Executive Officer, Zilla Parishad,Nagaon, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. |
14-02-2011 at 11:00AM (Public Hearing held at Khakanjuri Prathamik Bidyalay, Village - Khakanjuri, P.O. - Moderbheta, District - Nagaon, Assam ) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Expansion of Billet Manufacturing Unit (66,000MTPA to 150,000 MTPA) with Captive Power Plant (10MW) at Dag No. 144, Patta No.16, Mouza-Sila Sendurighopa, Village Mahekhaiti, Amingaon, District-Kamrup, Assam by M/s. Brahmaputra TMT Bars Pvt. Ltd. Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Kamrup district (Rural); District Industry Centre, Kamrup district; Bezera Anchalik Panchayat, Bezera, Kamrup, Assam; Chief Executive Officer, Zilla Parishad, Kamrup, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. Minutes of Public Hearing is available in DC office, Kamrup district (Rural); District Industry Centre, Kamrup district; Bezera Anchalik Panchayat, Bezera, Kamrup, Assam; Chief Executive Officer, Zilla Parishad, Kamrup, Assam; MoEF Regional Office at Shillong; PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. |
14-12-2010 at 11:00AM (Public Hearing held at open space in front of M/s. Brahmaputra TMT Bars Pvt. Ltd., Mouza-Sila Sendurighopa, Village Mahekhaiti, Amingaon, District-Kamrup, Assam ) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Expansion of Cement Plant (Cement 550 TPD PPC TO 1100 TPD PSC & PPC) and Clinker (400 TPD TO 700 TPD) at Village Sarutari, Tehsil Sonapur, Byrnihat, District Kamrup, Assam by M/s Purbanchal Cement Ltd. Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Kamrup district (Rural), District Industry Centre, Kamrup district, Town Committee, Vijaynagar, Kamrup, Assam, Chief Executive Officer, Zilla Parishad, Kamrup, Assam, MoEF Regional Office at Shillong,PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. Minutes of Public Hearing is available in DC office, Kamrup district (Rural), District Industry Centre, Kamrup district, Town Committee, Vijaynagar, Kamrup, Assam, Chief Executive Officer, Zilla Parishad, Kamrup, Assam, MoEF Regional Office at Shillong,PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. |
01-11-2010 at 11:00AM ( Public Hearing held at Tamulikuchi High School, Vill - Sarutari, 14th Mile, Byrnihat Kamrup)
|
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Cement Plant for Manufacture of Ordinary Portland Cement (OPC) and Portland Pozzolana Cement (PPC) and Cement Clinker for the capacity of 0.66 million TPA (2000 TPD) production at Jhoombasti, Debendra nagar in Badarpurghat tahsil of Karimganj district of Assam by M/s. Valley Strong Cement (Assam) Ltd. Executive Summary (in English) Executive Summary (in Assamese) Executive Summary (in Bengali)
EIA Report is available in DC office, Karimganj, District Industry Centre, Karimganj district, President Gaon Panchayat, Bundashil under Badarpur Anchalik Panchayat, Karimganj District, Zilla ParishadOffice, Karimganj district, MoEF Regional Office at Shillong, PCBA Regional Lab-cum-Office, Silchar & PCBA Head Office, Guwahati. Cover Page, Contents,Chapter-I, Chapter-II,Chapter-III, Chapter-IVChapter-V, Chapter-VI, Chapter-VII, Chapter-VIII,Chapter-IX,Annexure-III(I),Annexure-III(II),Annexure-III(III),Annexure-III(IV),Annexure-III(V)P(I) , Annexure-III(V)P(2) Minutes of Public Hearing is available in DC office, Karimganj, District Industry Centre, Karimganj district, President Gaon Panchayat, Bundashil under Badarpur Anchalik Panchayat, Karimganj District, Zilla ParishadOffice, Karimganj district, MoEF Regional Office at Shillong, PCBA Regional Lab-cum-Office, Silchar & PCBA Head Office, Guwahati. |
06-09-2010 at 11:00 A.M. (Public Hearing held at Vivekananda Kendra Vidyalaya, Debendra Nagar, PO: Badarpurghat, Dist-Karimganj, Assam)
|
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Drilling under Murkongselek at MSD by M/s. Oil India Ltd. Executive Summary (in English) Executive Summary (in Assamese)
EIA Report is available in DC office, Dhemaji, District Industry Centre, Dhemaji district, Jonai Town Committee, Dhemaji, Zilla ParishadOffice, Dhemaji district, MoEF Regional Office at Shillong, PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati. Cover Page, Contents, Baseline Study1, Baseline Study2,Baseline Study3, Baseline Study4,Baseline Study5,Baseline Study6, Baseline Study7, Baseline Study8, Baseline Study9, Drilling Programme, EIA, EMP, Conclusion, References, Appendices, Glossary Terms Minutes of Public Hearing dtd. 29-05-2010 is available in DC office, Dhemaji, District Industry Centre, Dhemaji district, Jonai Town Committee, Dhemaji, Zilla ParishadOffice, Dhemaji district, MoEF Regional Office at Shillong, PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati. |
29-05-2010 at 11:00 A.M. (Public Hearing held at Rukmini Ali ME School for MSD Jonai, Dhemaji District, Assam)
|
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed 45 KLPD Distillery unit at Khatkhati, Block Bokajan, District Karbi Anglong (Assam) by M/s. Radiant Manufacturers Pvt. Ltd. Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s. Radiant Manufacturers Pvt. Ltd. EIA Report is available in DC office, Karbi Anglong, District Industry Centre, Diphu Karbi Anglong district, Town Committee, Bokajan,Karbi Anglong district, Zilla Parishad Office, Karbi Anglong district, MoEF Regional Office at Shillong, PCBA Regional Office, Golaghat & PCBA Head Office, Guwahati. Front Page Index, Acknowledgement, Chapter-I, Chapter-II,Chapter-III, Chapter-IV, Chapter-V Ambient Air Quality Data |
17-02-2010 at 11:00 A.M. (Public Hearing held at Khatkhari Hindi L.P. School, PO -Khatkhati, Bokajan, Assam) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Drilling under Murkongselek at MSC & MSD by M/s. Oil India Ltd. Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s. Oil India Ltd. EIA Report is available in DC office, Dhemaji, District Industry Centre, Dhemaji district, Jonai Town Committee, Dhemaji, Zilla ParishadOffice, Dhemaji district, MoEF Regional Office at Shillong, PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati. Cover Page, Contents, Baseline Study1, Baseline Study2,Baseline Study3, Baseline Study4,Baseline Study5,Baseline Study6, Baseline Study7, Baseline Study8, Baseline Study9, Drilling Programme, EIA, EMP, Conclusion, References, Appendices, Glossary Terms Minutes of Public Hearing dtd. 10-02-2010 is available in DC office, Dhemaji, District Industry Centre, Dhemaji district, Jonai Town Committee, Dhemaji, Zilla ParishadOffice, Dhemaji district, MoEF Regional Office at Shillong, PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati. |
09-02-2010 at 11:00 A.M. (Public Hearing did not held for MSD Jonai, Dhemaji District, Assam)
10-02-2010 at 11:00 A.M. (Public Hearing held at Tari Bijoypur for MSC Jonai, Dhemaji District, Assam)
|
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Open Cast Project (0.25 MTPA) at Lekhapani under Tinsukia district, Assam by M/s Coal India Limited (North Eastern Coalfields), Margherita, Assam. Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s Coal India Limited (North Eastern Coalfields), Margherita, Assam. EIA Report is available in DC office, Tinsukia district, 9 Zila Parishad Committee Jagun, District Industry Centre, Lekhapani Gaon Panchayat, MoEF Regional Office at Shillong, Dibrugarh regional office of the Board, PCBA Head Office, Guwahati.. Cover Page Contents, Chapter-I, Chapter-II,Chapter-III(I),Chapter-III(II),Chapter-III(III),Chapter-III(IV), Chapter-IV(I),Chapter-IV(II), Chapter-V, Chapter-VI, Chapter-VII, Chapter-VIII,Chapter-IX,Chapter-X,Chapter-XI,Chapter-XII Minutes of Public Hearing dtd. 14-10-09 is available in DC office, Tinsukia district, 9 Zila Parishad Committee Jagun, District Industry Centre, Lekhapani Gaon Panchayat, MoEF Regional Office at Shillong, Dibrugarh regional office of the Board, PCBA Head Office, Guwahati |
14-10-2009 at 11:00AM (Public Hearing held at Lekhapani Forest IB, Lekhapani, Tinsukia, Assam) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed 200KLPD Grain Based Distillery, 15KLPD Malt Spirit, Bottling of IMFL, Country Liquor and 10MW Co-generation Power Plant by M/s NV Distilleries & Breweries (North East) Pvt. Ltd. Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s NV Distilleries & Breweries (North East) Pvt. Ltd. EIA Report is available in DC office, Kamrup district (Rural), District Industry Centre, Kamrup district, Town Committee, Vijaynagar, Kamrup, Assam, Chief Executive Officer, Zilla Parishad, Kamrup, Assam, MoEF Regional Office at Shillong,PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. Cover Page & Contents, Chapter-I, Chapter-II,Chapter-III, Chapter-IV, Chapter-V, Chapter-VI, Chapter-VII, Chapter-VIII,Chapter-IX, Annexure I,AnnexureII,Location Minutes of Public Hearing dtd. 15-09-09 is available in DC office, Kamrup district (Rural), District Industry Centre, Kamrup district, Town Committee, Vijaynagar, Kamrup, Assam, Chief Executive Officer, Zilla Parishad, Kamrup, Assam, PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. |
15-09-2009 at 11:00AM ( Public Hearing held at Proposed project site at Dag No. 20, 21 & 747 of No. 1 Tezpur village, P.O. Rampur, Mouza-Rampur, District-Kamrup, Assam) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Ropway Project between Guwahati and North Guwahati by Guwahati Metropolitan Development Authority. Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by Guwahati Metropolitan Development Authority. EIA Report is available in DC office, Kamrup district (Metro), District Industry Centre, Kamrup district, Town Committee, North Guwahati, Guwahati Municipal Corporation, Guwahati-1,Guwahati Metropolitan Development Authority, Guwahat-5, MoEF Regional Office at Shillong, PCBA Head Office, Bamunimaidam, Guwahati-21. Minutes of Public Hearing dtd. 26-08-09 is available in DC office, Kamrup district (Metro), District Industry Centre, Kamrup district, Town Committee, North Guwahati, Guwahati Municipal Corporation, Guwahati-1,Guwahati Metropolitan Development Authority, Guwahat-5, PCBA Regional Office, Bamunimaidam, Guwahati-21. |
25-08-2009 ( Public Hearing held at Circuit House, Kamrup (Metro) District Panbazar, Guwahati-1)
26-08-2009 (Town Committee Hall, North Guwahati, Kamrup (Metro) District)
|
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Drilling under Murkongselek at MSC & MSD by M/s. Oil India Ltd. Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s. Oil India Ltd. EIA Report is available in DC office, Dhemaji, District Industry Centre, Dhemaji district, Jonai Town Committee, Dhemaji, Zilla ParishadOffice, Dhemaji district, MoEF Regional Office at Shillong, PCBA Regional Office, Dibrugarh & PCBA Head Office, Guwahati. Cover Page, Contents, Baseline Study1, Baseline Study2,Baseline Study3, Baseline Study4,Baseline Study5,Baseline Study6, Baseline Study7, Baseline Study8, Baseline Study9, Drilling Programme, EIA, EMP, Conclusion, References, Appendices, Glossary Terms |
16-06-2009 (Posponed) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Mini Cement Manufacturing Unit (200 TPD) at Sarutari Village,Byrnihat Industrial area, Sonapur Circle, Kamrup(M) distict, Assam by M/s. Vinayak Cements Ltd. Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s. Vinayak Cements Ltd. EIA Report is available in DC office, Kamrup (M), District Industry Centre, Kamrup district, 55th Kamarkuchi Gaon Panchayat, Kamrup, Circle Office, Sonapur, Kamrup, Zilla Parishad,Kamrup district, MoEF Regional Office at Shillong, PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. |
11-05-2009 (Public Hearing held at factory Premises at Sarutari Village, Byrnihat Industrial area, Dist-Kamrup) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Cement Manufacturing Plant (200 TPD) at 15th Mile, GS Road, NH-40, Vill-Byrnihat, Sonapur, Kamrup distict, Assam by M/s. Shivshakti Cements. Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s. Shivshakti Cements. EIA Report is available in DC office, Kamrup (M), District Industry Centre, Kamrup district, 55th Kamarkuchi Gaon Panchayat, Kamrup, Circle Office, Sonapur, Kamrup, Zilla Parishad,Kamrup district, MoEF Regional Office at Shillong, PCBA Regional Office, Guwahati & PCBA Head Office, Guwahati. |
07-05-2009 (Public Hearing held at Suru Tandu LP School, Vill-Tandu, Byrnihat, Dist-Kamrup) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed 200 TPD VSK Cement Plant at Nagaon distict, Assam by M/s. Mahabali Cements Ltd. Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s. Mahabali Cements Ltd. EIA Report is available in DC office, Nagaon, District Industry Centre, Nagaon district, Changmaji Gaon Panchayat, Nagaon, Doboka Town Committee, Nagaon, Zilla Parishad,Nagaon district, MoEF Regional Office at Shillong, PCBA Head Office, Guwahati. |
05-05-2009 (Public Hearing held at Proposed Factory Premises at Modertuli, Doboka, Nagaon) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Manufacturing of Asbestos Cement Sheets at Changsari, Vill- Silla, Dist-Kamrup by M/s. Jumbo Roofings & Tiles. Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s. Jumbo Roofings & Tiles. EIA Report is available in DC office, Kamrup (Rural), District Industry Centre, Kamrup district, Dhopatari Gaon Panchayat, Kamrup, Circle Officer, North Guwahati, Kamrup district,Zilla Parishad,Kamrup district, MoEF Regional Office at Shillong, PCBA Head Office, Guwahati. |
02-05-2009 (Public Hearing held at Ganesh Mandir L. P. School, Vill- Silla, Haluguri Chowk, Changsari, Kamrup) |
||||||||||||||||||||||||||||||||||||||||||
|
a) Proposed Exploratory Drilling Project in Block AA-ONN-2004/1 at Mazgaon and Mora Bazar area of Amguri Block by M/s. Oil India Ltd. Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s. Oil India Ltd.(AMG1, AMG2, AMG3&4) EIA Report is available in DC office, Sivasagar, District Industry Centre, Sivasagar district, Amguri Town Committee,Zilla Parishad,Sivasagar district, MoEF Regional Office at Shillong, Regional Lab-cum-Office of the Board at Sivasagar, PCBA Head Office, Guwahati. Cover Page & Contents, Chapter-I, Chapter-II,Chapter-III, Diagram_Chapter-III, Chapter-IV, Chapter-V, Chapter-VI, Chapter-VII, Chapter-VIII, Appendix Minutes of Public Hearing dtd. 10-09-2008 is available in DC office, Sivasagar, District Industry Centre, Sivasagar district, Amguri Town Committee,Zilla Parishad,Sivasagar district, MoEF Regional Office at Shillong, Regional Lab-cum-Office of the Board at Sivasagar, PCBA Head Office, Guwahati. |
10-09-2008 (Public Hearing held at Amguri Natya Mandir, Amguri, Sivasagar, Assam) |
||||||||||||||||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||
|
a) Tikak Extension Open Cast Project (0.20 MTY) of M/s. Coal India Limited (North Eastern Coalfields). Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s. Coal India Ltd. EIA Report is available in DC office, Tinsukia district, Zila Parishad Office, District Industry Centre, Ledo Gaon Panchayat, Margherita Town Committee, MoEF Regional Office at Shillong, PCBA Head Office, Guwahati. Cover Page, Contents, Chapter-I, Chapter-II Chapter-III, Chapter-IV(i), Chapter-IV(ii), Chapter-V Chapter-VI, Chapter-VII, Chapter-VIII, Chapter-IX, Chapter-X, Chapter-XI, Chapter-XII
Minutes of Public Hearing dtd. 09-05-08 is available in DC office, Tinsukia district, Zila Parishad Office, District Industry Centre, Ledo Gaon Panchayat, Margherita Town Committee, MoEF Regional Office at Shillong, PCBA Head Office, Guwahati & Regional Office, Dibrugarh. |
09-05-2008
(Public Hearing held at Ledo Railway Club, Ledo, Assam) |
||||||||||||||||||||||||||||||||||||||||||
|
b) Ledo Open Cast Project (0.15 MTY) of M/s. Coal India Limited (North Eastern Coalfields). Executive Summary (in English) Executive Summary (in Assamese) Application form submitted by M/s. Coal India Ltd. EIA Report is available in DC office, Tinsukia district, Zila Parishad Office, District Industry Centre, Ledo Gaon Panchayat, Margherita Town Committee, MoEF Regional Office at Shillong, PCBA Head Office, Guwahati. Cover Page, Chapter-I, Chapter-II Chapter-III(i), Chapter-III(ii), Chapter-III(iii), Chapter-III(iv), Chapter-IV(i), Chapter-IV(ii), Chapter-V Chapter-VI, Chapter-VII, Chapter-VIII, Chapter-IX, Chapter-X, Chapter-XI, Chapter-XII
Minutes of Public Hearing dtd. 10-05-08 is available in DC office, Tinsukia district, Zila Parishad Office, District Industry Centre, Ledo Gaon Panchayat, Margherita Town Committee, MoEF Regional Office at Shillong, PCBA Head Office, Guwahati & Regional Office, Dibrugarh. |
10-05-2008
(Public Hearing held at Ledo Railway Club, Ledo, Assam)
|
|||||||||||||||||||||||||||||||||||||||||||
|
a) Mini Cement Plant Project of M/s. Raksha Cement (P) Ltd. |
30-04-2008
(Public Hearing held at proposed Factory Premises at Koraibari, Changsari, Kamrup Assam) |
||||||||||||||||||||||||||||||||||||||||||
|
b) Mini Cement Plant Project of M/s. Raksha Cement (P) Ltd. Executive Summary (in Assamese) Executive Summary is available in DC office, Kamrup district (Rural), Zila Parishad Office, District Industry Centre, Saraighat Gaon Panchayat, MoEF Regional Office at Shillong, PCBA Head Office, Guwahati. |
||||||||||||||||||||||||||||||||||||||||||||
| c) Application form submitted by M/s. Raksha Cement (P) Ltd. | ||||||||||||||||||||||||||||||||||||||||||||
| d) EIA Report is available in DC office, DC office, Kamrup district (Rural), Zila Parishad Office, District Industry Centre, Saraighat Gaon Panchayat, MoEF Regional Office at Shillong, PCBA Head Office, Guwahati. | ||||||||||||||||||||||||||||||||||||||||||||